To compare actual worked hours from your Timekeeping System (TKS) with the scheduled/planned hours in PMI, use the Labor Cockpit:
Steps to Check:
- Go to the Labor Cockpit
- Select the relevant department and date range
- Click the plus sign next to the date to expand the daily detail
- You’ll see:
- Scheduled hours (what was planned)
- TKS hours (what was actually worked and imported from your Timekeeping System)
- Hours broken down by productive and non-productive categories
You can also hover over bars in the graph to compare day-by-day totals visually.
Tip:
- If the numbers don’t match, check whether:
- The TKS import has been processed for the current period
- The department and role mappings between TKS and PMI are up to date
- Any manual adjustments were made in TKS or PMI after the import